
Current Projects - Fall 2023

A DRAFT rendering of The Greenspace building in Downtown Edgerton.
October 2023- Over the last month, the site has been graded, new utilities installed, building pad prepared, and the building foundations have been poured. Over the next couple of weeks, both overhead and underground utility work will be completed as well as construction of the building slab. The project schedule is on track with an estimated completion date of Summer 2025.
September 2023- Construction on The Greenspace is underway. It is anticipated to take approximately 14-18 months before the project is complete. The area has been fenced off. Please do not enter the construction zone for your safety.
August 2023-A groundbreaking for The Greenspace was held on August 11. Crews from Combes Construction will begin work in the coming weeks.
June 2023 - The Greenspace Project is out for bid. The Edgerton City Council is anticipated to award the project to the winning bidder in late July or early August.
The old brick garage and yellow house were torn down the first full week of June. While the debris has been removed, City crews will fence off the area for safety. Please do not enter any fenced off area.
The Greenspace is planned to be approximately 13,000 sq. feet and include a gymnasium, meeting spaces and event rooms, storm shelter, fitness center, outdoor stage and splash pad.
The City has contracted with Incite Design Studio to design the facility and hired Henderson Building Solutions as the City's Owner's Representative to manage the project.
Construction is expected to take 14-18 months to complete.
Crews from Harbour Construction will complete mill and overlay street improvements. Work will consist of milling existing roadway and adding a new asphalt overlay paving. Residents who live on W. 5th St., W. 3rd St. between Meriwood and Edgewood, and Meriwood between 1st and 3rd.
Cars should be moved off the street by 7:00 am. Work is tentatively scheduled to start October 23, weather permitting.
Residents in the impacted area should have received notification from the contractor. We appreciate your cooperation and patience during this work.
The City of Edgerton will complete a sanitary sewer rehabilitation project in 2023 to continue the work started in 2021. The goal is to reduce the amount of Inflow and Infiltration (I&I) of stormwater into the sanitary sewer system. I&I increases costs for customers by unnecessarily treating rain or storm runoff.
The Project will take place East of the 2021 CDBG Project, consisting of Cured In Place Pipe (CIPP), Manhole Patches, and Point Repairs. The project area covers the sewer line between Nelson Street and Martin Street, from E. 5th Street to W. 4th Street.
The City of Edgerton has contracted Tetra Tech Inc., Consulting Engineers to evaluate the sanitary sewer system. The project involves the inspection of manholes and sanitary sewer lines using various nonintrusive/nondestructive testing methods.
Crews will identify and record defects for rehabilitation that will reduce the potential for dry weather system backups and wet weather overflows. Once this evaluation is complete, the City will solicit bids for a company to complete the CIPP and other repairs.
Funding for this project comes from a Community Development Block Grant and the Sewer Fund.

The design for Glendell Acres Park includes a new skate park, playground area, walking path and pavilion.
UPDATE: October 2023 - The final design of the park and Skate Spot is expected to be completed in the next couple of months. Once final design is completed, the City will select a contractor to begin construction. Construction is now expected to start in 2024.
UPDATE: June 2023 - The Edgerton City Council approved a design/build agreement with American Ramp Company for the skatepark component of the park renovation.
UPDATE: April 2023 - City Council members selected a post-and-deck style playground and a ninja warrior style fitness system for the park renovation project.
UPDATE: February 2023 - The Edgerton City Council agreed to pre-purchase playground equipment for the Glendell Acres Park Renovation. Playground equipment currently is experiencing long lead times for delivery and pricing volatility.
ORIGINAL POST: The Edgerton City Council has approved a contract with SWT Design to redesign Glendell Acres Park on Edgewood Street. The City and SWT Design conducted a survey throughout the month of July to collect public opinions on the options for the renovations.
This project includes the design and renovation of the park with new equipment, a finished sidewalk system, re-purposed greenspaces and landscaping. The approved Parks Master Plan will govern the general design theme of the project.
This project is paid for though Park Impact Fees, the majority of which comes from development at LPKC.
The 2nd Street Reconstruction Project will improve one of the more heavily traveled routes through Edgerton. The project calls for street improvements, stormwater improvements, installation of trails, and streetlighting to make the road safer for both drivers and pedestrians.
The project includes reconstruction of of E 2nd Street from Nelson St to City Limits and W Edgewood Drive from E 2nd Street to W 4th Street . This project is in preliminary design, we expect final design plans in 2024.
City Council approved a contract with Renaissance Infrastructure Consulting (RIC) to complete a land survey and preliminary design for the project. Homeowners along 2nd Street may notice utility marking flags in their yards as part of this process.