DAMAC Data Center

The City of Edgerton has received applications for Preliminary Plat and Final Site Plan for DAMAC Digital. 

This project is located in an existing building at 31800 West 196th Street in Logistics Park Kansas City. The property is currently zoned Logistics Park (L-P) which allows data centers as a permitted use.  

Actions:

5/12 Planning Commission Meeting

  • Planning Commission approved the Preliminary Plat and tabled the Final Site Plan until more information is provided

6/9 Planning Commission Meeting

  • Planning Commission voted to reject the final site plan

Frequently Asked Questions:


NO. DAMAC Digital is using advanced technology called a closed-loop cooling system. This type of cooling system is very different from systems in older data centers.  

A closed-loop system protects the City’s water resource. After the initial one-time fill of the system, there is no use of the public water supply for the system. This advanced technology is designed for maximum water efficiency, typically achieving a Water Usage Effectiveness (WUE) near zero.  

NO. This facility will be engineered with strict attention to noise management, with measures designed to meet or exceed noise regulations.

The closed-loop cooling system is significantly quieter than older technology. In fact, when we measured the decibel level at the property line for similar projects, we couldn’t hear anything beyond normal ambient noise like wind blowing and birds chirping. Standing near the property line, this advanced technology is quieter than a car driving byyour home’s exterior air conditioning unitor even normal conversation. Especially for this Project, traffic travelling on Interstate 35 will be louder than noise produced at this building.